Clinton Lloyd Consultancy (CLC) was appointed as Client Project Manager for the development of a new 15,000m² medical device manufacturing facility, comprising ISO 8 classified and unclassified cleanrooms, warehousing, office accommodation and an on-site café.

Responsible for overseeing all construction-related aspects of the project, CLC managed the development through the RIBA Plan of Work stages, from initial design through to completion and handover.

Our role included the procurement and appointment of external design consultants and the Principal Contractor, along with coordinating the wider project team to ensure the specialist requirements of the manufacturing facility were incorporated into the design and construction process.

The project was successfully delivered over an 18-month period, from commencement of design through to handover, bringing together specialist manufacturing environments and supporting facilities within a single purpose-built development.

Key Project Highlights

  • 15,000m² new-build medical device manufacturing facility.
  • ISO 8 classified and unclassified cleanroom environments.
  • Integrated warehousing, offices and staff café.
  • Client-side project management across the RIBA stages.
  • Procurement and management of external design consultants and Principal Contractor.
  • 18-month programme from design commencement to handover.